Maeshowe research project
1998/1999 project plan

The status of this project plan

Goal of the pilot

This project plan describes all the activities, timing, organization and costs involving the set up of  investigations at Maeshowe in 1998/1999. The main goals are derived from the results of the project in 1997/1998.
The main goals for doing this pilot, which ends Febr. 1, 1999, are many fold:

Activities and their timing

The following planning is made (the organisations/people that take part can be found in the section Organization):
     
  1. Activity: determine how the sunset will be presented at Tormiston Mill

  2. Description: This will be done using a PC/TV convertor. The cabling has been finalized.
    Action by: Victor Reijs
    Start date: March 1, 1998
    End date: Aug. 31, 1998
    Actual date: Sept. 15, 1998
  3. Activity: Investigate technical possibilities for dial-in or direct connection and IAP

  4. Description: Finding sponsor for dial-in connection (ISDN) or direct link and IAP (Internet Access Provider).
    Action by: Victor Reijs and Charles Tait
    Start date: March 1, 1998
    End date: Aug. 31, 1998
    Actual date: Sept. 29, 1998
  5. Activity: Investigate the way how to make the promotional video

  6. Description: finding out how to make it (with what equipment) and what scenario/script.
    Action by: Victor Reijs and Charles Tait
    Start date: March 1, 1998
    End Date: Dec 11, 1998
    Actual date: posponed
  7. Activity: Find sponsors for this project

  8. Description: Finding sponsor for the equipment and travel needed in this project. Already found sponsors are: SURFnet bv (a Dutch projectplan for these activities can be found here), UU Physics , Alligator Descartes and you???
    Action by: Victor Reijs and Charles Tait
    Start date: March 1, 1998
    End date: Nov. 30, 1998
    Actual date: Dec 1st, 1998
  9. Activity: Investigate effect of Maeshowe 1997/1998 project

  10. Description: Investigate if 1997/1998 project has increased the amount of visitors for Maeshowe and Orkney in general in 1998.
    Action: Historic Scotland, Orkney Tourist Board
    Start date: March 15, 1998
    End date: Dec. 1, 1998
    Actual date: posponed
  11. Activity: Decision process within Historic Scotland

  12. Description: Historic Scotland has to discuss internally if they will support this continuation of the project
    Action by: Historic Scotland
    Start date: March 15, 1998
    End date: May 1, 1998
    Actual date: Aug 10, 1998
  13. Activity: Decide on PR and liability strategy around 1998/1999 broadcasts

  14. Description: Decisions have to be taken and implemented with regard to WWW pages, advertisements in internal Historic Scotland newsletter, Orcadian newspapers, etc. Furthermore the liability in case of problems need to be finalized.
    Action by: Victor Reijs, Charles Tait, Historic Scotland
    Start date: April 1, 1998
    End date: Dec. 1, 1998
    Actual date: Dec 10th, 1998
  15. Milestone: Approval from Historic Scotland

  16. Planned date: May 1, 1998
    Actual date: Aug. 10, 1998
  17. Milestone: Final project plan ready

  18. Planned date: May 1, 1998
    Actual date: Oct. 3, 1998
  19. Activity: testing other broadcasting techniques

  20. Description: Beside the periodically update web picture, things like IP multicast and application using that (like Real or Icast of vic) will be tested
    Action by: Victor Reijs
    Start date: Nov. 9, 1998
    End date: Nov.13, 1998
    Actual date: Nov. 13, 1998
  21. Activity: installing ISDN

  22. Description: Installing ISDN at Tormiston Mill/Maeshowe
    Action by: BT
    Start date: Sept. 29, 1998
    End date: Oct. 15, 1998
    Actual date: Nov. 4, 1998
  23. Activity: making shots for the promotional video

  24. Description: Shot will be made for the promotional video of the sunsets and the Maeshowe environment
    Action by: Charles Tait and Victor Reijs
    Start date: Nov.1, 1998
    End date: Febr.1, 1999
    Actual date: posponed
  25. Activity: Installing video- and PC equipment

  26. Description: Equipment will be installed at Tormiston Mill and/or the mound
    Action by: Victor Reijs, Charles Tait and Historic Scotland
    Start date: Nov. 29, 1998
    End date: Nov. 30, 1998
    Actual date: Dec 1st, 1998
  27. Activity: Make mock-up of passage blocking stone

  28. Description: To determine the light path changes due to the passage blocking stone a mock-up will me made.
    Action by: Victor Reijs and Charles Tait
    Start date: Nov. 29, 1998
    End date: Jan. 10, 1998
    Actual date: Dec. 31, 1999
  29. Activity: Run the broadcast and measurements with regard to blocking stone

  30. Description: The people that initiated the megalithic cam page for Maeshowe will be present at Maeshowe, to see how things are working and try to get an automated working system.
    Action by: Victor Reijs, Charles Tait, Historic Scotland
    Start date: Dec. 2, 1998
    End date: Dec. 11, 1998
    Actual date: Dec. 11, 1998
  31. Milestone: Decision if automated run is possible

  32. Action: Victor Reijs, Charles Tait
    Planned date: Dec. 11, 1998
    Actual date: Dec. 11, 1998
  33. Activity: Automated run

  34. Description: The equipment is able to run without any attendance (beside perhaps change videotapes/film).
    Action: Equipment;-)
    Start date: Dec. 13, 1998
    End date: Febr. 1, 1999
    Actual date: Jan 31, 1999
  35. Activity: making the promotional video

  36. Description: A promotional video will be made of the sunsets and the Maeshowe environment
    Action by: Charles Tait and Victor Reijs
    Start date: March 1, 1999
    End date: June 1, 1999
    Actual date: posponed
  37. Milestone: End of pilot

  38. Planned date: June 1, 1999
    Actual date:

Organization aspects of project

The project will be run with the following people as initiators: Victor Reijs (project leader), Charles Tait and Historic Scotland. The sponsors for this project will be drawn from local Orkney/Scottish enterprises if possible. If needed, other sponsors can be involved.

Communication channels

The communication within the project will be done with several methods:

Costs

The following costs (estimated from the results of the 1997/8 project) can be seen below (until Feb. 1999). This list excludes manpower, but includes 33% of the equipment costs* (a write off of 3 years): So this project could cost around £ 4 315, excluding man power (some 1000 hours). With the help of  the sponsors this is not always real money!


Disclaimer and Copyright


Last content related changes: Febr. 10th, 1999